Contact us

Transformation benefits belong in the budget, not the status report

Status reports track the plan, not the benefit, so give each benefit an owner in the business and a budget line, and report whether the change is used.

CoghlanElms · 7 min read

Key points

  • Victorian agencies rated 85% of 113 major projects green for benefits; when the auditor examined 10 closely, it rated all 10 amber.
  • In a federal transformation of 100 projects, no status or closure report recorded savings, and the auditor found its savings could not be calculated.
  • Give each benefit an owner in the business and a line in their budget, report whether the change is used, then close the office.

Transformation programs are funded for the benefits in their business case. Once approved, they report progress against the plan: milestones met, money spent and a colour for each. Audits of Victoria's major projects show how far that colour can sit from the benefits.

In 2024 the Victorian Auditor-General's Office (VAGO) asked agencies, for the first time, to rate their major projects on benefits. They rated 96 of 113 projects (85%) green, meaning they believed their systems to measure benefits were well developed1. In its own detailed review of 10 projects, VAGO rated all 10 amber. Most often the baseline data was incomplete, or there was no evidence of a process to measure benefits. Nor was it clear which agency would measure them, or at what point1. VAGO chose the 10 for their cost or for large changes to cost or time, so they may not be typical1.

A status report shows progress on the plan. Benefits are made in the business: in who owns them, which budget carries them and whether the change is used.

A status report measures the plan

A status rating answers one question: is the work on track against what has been approved? VAGO's 2025 review makes this explicit. Agencies rate each project against its current approved parameters, so a project can stay green after a change to scope, cost or completion date if the change was approved2. Of the 110 projects surveyed, 35 (31.8%) had needed ministerial or government approval for at least one significant scope change2.

Changes of that size should prompt a fresh look at the benefits. In the 2024 survey, 101 of 113 projects (89%) said they had a process to recalculate benefits after a significant scope change1. Yet some case-study projects had changed significantly in scope, cost and time without reassessing the timing or scale of their benefits. Some had not revisited their benefit–cost ratio1.

Your program can be re-planned, re-approved and still report green, while the benefits it was funded for go unchecked.

Savings outside a budget line go unseen

A federal program shows the same gap. A large agency formally began a transformation in 2015, with a program office and six strategic programs overseeing 100 projects3. Savings were not its main purpose. Even so, the Australian National Audit Office (ANAO) found in 2017 that costs and savings had gone untracked for the program and most of its projects. Of 41 projects with closure reports and 51 with status reports, none reported savings3.

From April 2017, the agency reported financial benefits internally. It defined a harvestable benefit as one that produces a direct budget saving, and no project identified one. Of the five closed projects reported, one had a verified saving, of $45,000. The agency classed it as notional: a saving that cannot be reinvested3.

Another ANAO audit, of a federal department's savings measures, shows the other side. It covered selected 2014–15 and 2015–16 Budget measures meant to deliver $1.2 billion in savings and other benefits4. Savings taken from program funding were implemented and monitored well. The department had no arrangements to monitor its own efficiency savings, so it could not be sure they were achieved4.

In our reading, the difference is where the saving sits. A cut to a funding line shows in the next budget. A saving kept inside the organisation shows only if someone owns it and looks for it.

Each benefit needs an owner in the business

Commonwealth policy already says where benefits belong. The Digital Transformation Agency's (DTA) benefits management policy has applied to agencies' digital and ICT funding proposals since 24 July 2023. It states that "Benefits are owned by business units, and not by the project"5. Its guidance asks for one owner per benefit, in a business-as-usual role, because ownership usually outlasts the project. At closure, responsibility passes formally to those owners6.

In Victoria, VAGO found benefit plans that left open who would measure longer-term benefits. Some counted on data that third parties might collect one day, not data the sponsoring agency or end user would hold1.

We would go further and give each benefit a line in its owner's budget. A financial benefit becomes a lower budget, or a decision on where the freed money or staff go next. The ANAO noted that verifying benefits could let the agency put them to use, such as by returning savings to consolidated revenue3. A benefit that is not financial goes into the owner's performance reporting, as the DTA's policy also expects5.

Report use, not tasks done

Some benefits depend less on what a program builds than on what the organisation stops doing. In July 2015, a federal agency began replacing its welfare payment system, planned as five tranches to June 2022 at about $1.5 billion7. It was to return $312 million a year to government from year eight, and end by switching off the old system7. Funding came one tranche at a time. Before each, the agency reported to government on the deliverables achieved7.

In 2020 the ANAO found that delays to switching off the old system put all the expected benefits at risk of delay or loss. In June 2020 the switch-off was confirmed as the main goal, yet almost half of it was not expected to finish within the program. The old system's operating costs were not being monitored either7.

The UK National Audit Office (NAO) drew a similar lesson from six completed or long-running projects: a project's value lies in how people take up and use what it delivers8.

We would report use beside the milestones: the share of work on the new process, the old systems switched off, and the cost of running both until then.

Close the office when owners carry the benefits

A program office is set up to deliver a plan, so it tends to close when the plan is done. If the benefits still sit with it, they lose their owner when it goes. The NAO's earlier work found that government does not routinely look at what happens after major projects are completed8. Experts told the NAO that government's effort goes into winning funding and meeting budget and schedule, less into whether projects achieve their purpose8. In Victoria, the Department of Treasury and Finance's gateway guidance expects a benefits review 6 to 12 months after completion1.

So we would not close the office at the last milestone. We would close it when the change is in use, each benefit sits in an owner's budget or performance reporting, and the first benefits review has a date.

Agencies rated most projects green for benefits; VAGO rated its 10 amber
Benefits rating, 2024Agencies' self-assessmentVAGO's detailed review
Green960
Amber910
Red00
Not applicable80
Projects rated11310

Source: VAGO, Major Projects Performance Reporting 20241. Sample: 113 major projects of $100 million or more surveyed in 2024; 10 case-study projects chosen for high cost or large changes.

Of five closed projects, one had a verified saving: $45,000
Closed projects reportedFinancial benefit
TwoCould not be verified: no baseline set
One$45,000 in notional savings, verified
One$5.5 million in notional savings, not yet verified
OneNone realised

Source: ANAO, Costs and Benefits of the Reinventing the ATO Program, 20173. Sample: the five closed projects in the program's internal benefit reports, April to June 2017.

The program's return depended on switching the old system off
Welfare payment system programPlanned in 2015Found by the ANAO in 2020
Return to government$312 million a year from year eightAll expected benefits at risk of delay or loss
Old systemSwitched off by 30 June 2022Almost half not due to finish by the program's end
ScheduleFive tranches, July 2015 to June 2022Tranches extended; four and five merged

Source: ANAO, System Redevelopment — Managing Risks While Planning Transition, 20207. Sample: one federal program, July 2015 to mid-2020.

Where to start

  • List the benefits in your business case and name one owner for each, in a business role that will outlast the program.
  • Put each financial benefit in its owner's budget, as a lower line or a decision on where the freed money or staff go. Put the other benefits in that owner's performance reporting.
  • Add measures of use to every status report: the share of work running through the new process, and the old systems and steps switched off.
  • When scope, cost or timing changes, re-estimate the benefits before you re-approve the plan.
  • Close the program office when the change is in use and every benefit has an owner, and set a date to review the benefits after closure.

Related insights

Sources

  1. Victorian Auditor-General's Office (VAGO). Major Projects Performance Reporting 2024. Tabled 19 February 2025; survey of 113 major projects and 8 case studies in 2024. Accessed 7 October 2026.
  2. Victorian Auditor-General's Office (VAGO). Major Projects Performance Reporting 2025. Tabled 4 March 2026; survey of 110 major projects in 2025. Accessed 7 October 2026.
  3. Australian National Audit Office (ANAO). Costs and Benefits of the Reinventing the ATO Program, Auditor-General Report No. 15 of 2017–18. Published 22 November 2017; program from 2015 to mid-2017. Accessed 7 October 2026.
  4. Australian National Audit Office (ANAO). The Design, Implementation and Monitoring of Health's Savings Measures, Auditor-General Report No. 51 of 2017–18. Published 27 June 2018; measures from the 2014–15 and 2015–16 Budgets. Accessed 6 October 2026.
  5. Digital Transformation Agency (DTA). Benefits Management Policy (CAP2.POL32). Applies from 24 July 2023. Accessed 6 October 2026.
  6. Digital Transformation Agency (DTA). Benefits Management guides and tools. Undated guidance supporting the policy, current at access. Accessed 7 October 2026.
  7. Australian National Audit Office (ANAO). System Redevelopment — Managing Risks While Planning Transition, Auditor-General Report No. 10 of 2020–21. Published 24 September 2020; WPIT from July 2015 to mid-2020. Accessed 7 October 2026.
  8. National Audit Office (UK). Lessons learned: Delivering value from government investment in major projects, HC 554, Session 2023–24. Published 23 February 2024; six projects, fieldwork September 2023 to January 2024. Accessed 6 October 2026.

Start with a conversation.

Tell us what you need to change. We will show you how we would approach it.

Contact us