Key points
- Ten of 11 comparable transmission projects in the market operator's last two plans now expect full capacity later, four by about two years or more.
- Approvals, land access, community consent and contracting shape those dates, alongside the workforce and supply pressures owners cannot control.
- Plan that work with the engineering from the business case, gate each commitment on evidence, and report forecasts as ranges across the portfolio.
The Australian Energy Market Operator (AEMO) published its 2026 Integrated System Plan (ISP) in June. It finds the National Electricity Market needs about 6,000 km of new transmission by 2050, on top of today's 44,000 km1. The build needed to 2030 is faster than has been achieved to date. While two recent projects were under construction, lines went up at about 365 km a year1. AEMO says the planning is clear and the task now is delivery1.
Delivery is where the dates are moving. Of 11 comparable projects in both the 2024 and 2026 plans, ten now expect to reach full capacity later1,2. Costs have moved too. After inflation, some estimates prepared in 2025 were around double those used for the 2024 plan3.
It is easy to read this as an engineering and supply problem, and part of it is. But regulators, Victoria's Auditor-General and the network businesses also point to approvals, land, consent and contracts. That is organisational work, and the owner runs it.
The schedule is set before construction starts
A transmission line cannot be built until its route is approved and its land is secured. AEMO treats a project as committed only once five tests are met: site acquired, components ordered, approvals, finance and construction timing1. None of the five is a design milestone.
In 2021, Victoria's Western Renewables Link was expected to be complete in 2025. By July 2025, the expected date was 20294. Construction cannot begin until a planning scheme amendment is made, which is expected in late 2026. The VNI West interconnector, in turn, cannot be commissioned until the link is in service4.
In Infrastructure Australia's 2025 survey, about six in ten organisations rated each of materials costs, labour costs and skills shortages a major or significant disruption5. Almost half (47%) also named delays in planning and environmental approvals among the greatest risks5. Owners cannot set the price of materials or the size of the workforce. They can decide when approvals work begins. Infrastructure Australia found that in energy, environmental approvals are often left until late. Some teams reach them only after the business case, funding, timeline and design are settled, then find the requirements as they go5.
Consent and land are delivery work
Community consent can look like a communications task. The evidence puts it on the schedule. In December 2023, the Australian Energy Infrastructure Commissioner completed a federal review of community engagement on renewable energy infrastructure, including transmission6. It found poor engagement had produced significant distrust of developers, especially those proposing new long-distance lines. It judged many developers' engagement teams, and the way that work was governed, to be below what communities expect6. A landholder asked to host a line might wait years to learn what they would be paid6. The government accepted all nine recommendations in full or in principle. After a final progress report in May 2026, it notes that concerns about social licence continue7.
Regulation now treats engagement as a delivery risk. Under a rule made in November 2023, transmission businesses must engage landowners, councils, residents, environmental groups and traditional owners early on ISP projects. The Australian Energy Market Commission (AEMC) expects this to improve planning by exposing risks to the schedule sooner8. The Australian Energy Regulator (AER) expects early engagement to make cost forecasts more accurate, because community input can change a route. It is more likely to reject or reassess a project's cost application where engagement has been insufficient9.
Plan approvals, land and procurement with engineering
Costs tell the same story as dates. AEMO's updated cost database, published in 2025, prices overhead lines 25% to 55% higher than in 2023, after inflation, depending on scope3. Network businesses and planning bodies gave AEMO six main drivers. Three concern the market and the terrain: supply chain pressure, competition among concurrent projects, and complex projects in remote areas. The other three concern how the work is organised. They are community and landholder engagement, scope revisions as assessments are completed, and the cost of allocating risk in contracts3.
The rules have moved to bring this work forward. Since September 2024, transmission businesses can seek to recover the cost of early works before the regulatory investment test is complete. The AEMC describes early works as including stakeholder engagement, corridor assessment, ordering long-lead equipment, preparing planning approvals and acquiring easements. It expects earlier work to cut the risk of delays and of costs rising later10.
Procurement timing matters as well. AEMO notes that early investment may help Australia hold its place as countries compete for the same equipment1. Industry told Infrastructure Australia that as energy projects slip, local firms hesitate to build their workforce, and overseas suppliers may lose interest5.
We would run these streams as one program from the business case, on one schedule with named owners.
Govern the portfolio with gates and ranges
Large projects rarely keep their first estimates. Reviewing megaproject research, Bent Flyvbjerg of Oxford University reports that nine in ten such projects overrun their budgets. The pattern has held for the 70 years for which comparable data exist11. In his account, projects break when early estimates meet real conditions, then stop and reorganise. His remedy is better management of the front end, before the decision to build11.
Victoria shows how quickly a forecast can be overtaken. Its 2025 transmission plan assumed, in its delay scenario, that new projects would slip by no more than a year to 2040. By December 2025, the Auditor-General noted that AEMO had announced two-year delays for two key projects4. AEMO's own plan now tests a slower case, with transmission projects six months to two years late and costs 30% higher. In that case the 2030 renewables target would be missed1.
The regulator already describes the governance it expects. The AER expects owners of large transmission projects to show clear accountability for decisions that could cause overruns or delays. It also expects regular review points, gateway decisions and reporting against budget and schedule9. We would apply it across the whole portfolio, reporting forecasts as ranges and showing how projects depend on each other.
| Project | 2024 plan | 2026 plan |
|---|---|---|
| HumeLink | July and December 2026 | December 2027 |
| Project EnergyConnect Stage 2 | July 2027 | November 2027 |
| Western Renewables Link | July 2027 | November 2029 |
| Hunter-Central Coast network | December 2027 | July 2028 |
| Central-West Orana network | August 2028 | December 2028 |
| Sydney Ring North | December 2028 | November 2029 |
| Gladstone Project | March 2029 | Mid-2030 |
| CopperString | June 2029 | 2032 |
| VNI West, Victoria to New South Wales | December 2029 | November 2031 |
| Project Marinus Stage 1 | December 2030 | December 2030 |
| Project Marinus Stage 2 | December 2032 | December 2034 |
Source: AEMO, 2024 and 2026 Integrated System Plans, June 2024 and June 2026; full-capacity timing advised by proponents1,2. Sample: 11 projects in both plans; two others changed scope.
| Slower-delivery case | Assumption or result |
|---|---|
| Committed transmission projects | 6 months late |
| Anticipated projects | 12 months late |
| Actionable and future projects | 2 years late on average |
| Project capital costs | 30% higher on average |
| Renewable share of supply, 2030 | 75%, against an 82% target |
Source: AEMO, 2026 Integrated System Plan, Constrained Delivery sensitivity, modelled to 20301. Sample: generation, storage and transmission in the National Electricity Market.
Where to start
- Build approvals, land access and engagement into the business case alongside the engineering, with one schedule, one cost baseline and named owners.
- Use AEMO's five commitment tests as gate evidence. Before committing to a date, show which of site, components, approvals, finance and construction timing are in place.
- Start early works as soon as a project enters the plan, including engagement, corridor assessment and long-lead orders. Fund them as project costs, not overhead.
- Test every forecast against delivered projects rather than plans. Report dates as ranges, with the basis for each and what has moved since the last report.
- Show the whole portfolio on one page, with the dependencies between projects, so the board sees where a slip in one lands in the others.